97/N Central Ave. Road Repair Project to Move Forward

0
1265

Marshfield, WI (OnFocus) Repair work to WIS-97/North Central Ave. is set to begin in May.

Under the terms of the contract, work can commence May 1 with required completion by August 29. The Wisconsin DOT expects a schedule shortly for the project, said project manager Mark Steidl. The prime contractor is S&N Inc., from Merrill.

From Arnold Street and Harrison Street in Marshfield, the project will remove and replace the asphalt surface, upgrade sidewalk curb ramps to ADA standards, repair curbs, and improve traffic signal and median island construction at Arnold Street and Doege Street.

Originally scheduled for 2018, the project was delayed last May after the single bid came in higher than expected. New bids were due in December.

97/Central Avenue Bid Process Delayed

State Re-evaluates HWY 97 Project (North Central Avenue)

News Desk
Author: News Desk

This piece was posted by our news team! Contact us or submit stories at [email protected].